Lea County Road Department

 

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

 

RECORD FOR MONTHLY REPORT JANUARY 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 10
BASE HAULED

6,846 TONS

PIT RUN HAULED 0 TONS
ASPHALT ROADS WORKED ON 0
PATCH YARDS USED

38  YARDS

BBLS.WATER 3,320 BBLS.
CHIPS HAULED 0  TONS 
ROADS CHIP SEALED 0
TREE TRIMMING 2   DAYS
TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

227.75 MILES

CATTLE GUARD CREW  
GUARDS CLEANED 9
GUARDS REPAIRED 4
GUARDS RE-SET 1
GUARD REPLACED 2
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 0 TONS
BASE MATERIAL MOVED TO LOADING AREA 3,000 TONS
MATERIAL  LOADED FOR ROADWAYS 6,846 TONS
PIT RUN  
PUSHED UP 2,010 TONS
PIT RUN MOVED TO STOCK PILE  0 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 1,500 TONS
PIT RUN FROM COUNTRY CLUB 0 TONS
N.M.ONE CALLS    
ONE CALLS MADE 198
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

2
911 SIGNS MISSING REPLACED 1
SIGNS REPLACED MISSING 20
SIGNS REPLACED DAMAGED 12
SIGN AND POST INSTALLATION 6
COUNTY MOWING   
NO MOWING ACTIVITY  
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 13 PROJECTS
WELDING SHOP ACTIVITIES 16 PROJECTS
MECHANIC WORK, SHOP SERVICE, FIELD SERVICE 64 UNITS
 
 

Return to top of page

 

 

RECORD FOR MONTHLY REPORT FEBRUARY 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 4
BASE HAULED

862 TONS

PIT RUN HAULED 3,284 TONS
ASPHALT ROADS WORKED ON 0
PATCH YARDS USED

43  YARDS

BBLS.WATER 6,680 BBLS.
CHIPS HAULED 692  TONS 
ROADS CHIP SEALED 0
TREE TRIMMING 6   DAYS
TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

298 MILES

CATTLE GUARD CREW  
GUARDS CLEANED 14
GUARDS REPAIRED 6
GUARDS RE-SET 2
GUARD REPLACED 1
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 3,322 TONS
BASE MATERIAL MOVED TO LOADING AREA 3,307 TONS
MATERIAL  LOADED FOR ROADWAYS 814 TONS
PIT RUN  
PUSHED UP 2,850 TONS
PIT RUN MOVED TO STOCK PILE  2,987 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 0 TONS
PIT RUN FROM COUNTRY CLUB 0 TONS
N.M.ONE CALLS    
ONE CALLS MADE 150
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

2
911 SIGNS MISSING REPLACED 1
SIGNS REPLACED MISSING 24
SIGNS REPLACED DAMAGED 8
SIGN AND POST INSTALLATION 6
COUNTY MOWING   
NO MOWING ACTIVITY  
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 49 PROJECTS
WELDING SHOP ACTIVITIES 16 PROJECTS
MECHANIC WORK, SHOP SERVICE, FIELD SERVICE 83 UNITS

 

 

Return to top of page

 

 

RECORD FOR MONTHLY REPORT MARCH 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 1
BASE HAULED

385 TONS

PIT RUN HAULED 1,272 TONS
ASPHALT ROADS WORKED ON 1
PATCH YARDS USED

36  YARDS

BBLS.WATER 6,360 BBLS.
CHIPS HAULED 620  TONS 
ROADS CHIP SEALED 0
TREE TRIMMING 4   DAYS
TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

384 MILES

CATTLE GUARD CREW  
GUARDS CLEANED 2
GUARDS REPAIRED 4
GUARDS RE-SET 0
GUARD REPLACED 1
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 652 TONS
BASE MATERIAL MOVED TO LOADING AREA 1,458 TONS
MATERIAL  LOADED FOR ROADWAYS 96 TONS
PIT RUN  
PUSHED UP 5,800 TONS
PIT RUN MOVED TO STOCK PILE  7,520 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 0 TONS
PIT RUN FROM COUNTRY CLUB 1,272 TONS
N.M.ONE CALLS    
ONE CALLS MADE 180
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

0
911 SIGNS MISSING REPLACED 0
SIGNS REPLACED MISSING 12
SIGNS REPLACED DAMAGED 2
SIGN AND POST INSTALLATION 0
COUNTY MOWING   
NO MOWING ACTIVITY  
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 92 PROJECTS
WELDING SHOP ACTIVITIES 22 PROJECTS
MECHANIC WORK 16 UNITS
SHOP SERVICE 16 UNITS
FIELD SERVICE 20 UNITS

 

 

Return to top of page

 

 

RECORD FOR MONTHLY REPORT APRIL 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 1
BASE HAULED

1,508 TONS

PIT RUN HAULED 216 TONS
ASPHALT ROADS WORKED ON 0
PATCH YARDS USED (using Dura Patcher)

14  YARDS

BBLS.WATER 7,400 BBLS.
CHIPS HAULED 533  TONS 
ROADS CHIP SEALED (Working on S. Maddox) 0
OIL USED HFE/PPE 6,700 Gal / 3,800 Gal
TREE TRIMMING

 2 DAYS

TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

409.9 MILES

CATTLE GUARD CREW  
GUARDS CLEANED 6
GUARDS REPAIRED 4
GUARDS RE-SET 2
GUARD REPLACED 5
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 1,726 TONS
BASE MATERIAL MOVED TO LOADING AREA 1,066 TONS
MATERIAL  LOADED FOR ROADWAYS 18 TONS
PIT RUN  
PUSHED UP 2,500 TONS
PIT RUN MOVED TO STOCK PILE  2,375 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 1,508 TONS
PIT RUN FROM COUNTRY CLUB 216 TONS
N.M.ONE CALLS    
ONE CALLS MADE 163
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

2
911 SIGNS MISSING REPLACED 1
SIGNS REPLACED MISSING 12
SIGNS REPLACED DAMAGED 3
SIGN AND POST INSTALLATION 6
COUNTY MOWING   
NO MOWING ACTIVITY  
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 30 PROJECTS
WELDING SHOP ACTIVITIES 13 PROJECTS
MECHANIC WORK 28 UNITS
SHOP SERVICE 12 UNITS
FIELD SERVICE 14 UNITS

 

 

Return to top of page

 

RECORD FOR MONTHLY REPORT MAY 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 1
BASE HAULED

1,634 TONS

PIT RUN HAULED 214 TONS
ASPHALT ROADS WORKED ON 1
PATCH YARDS USED (using Dura Patcher)

10  YARDS

BBLS.WATER 7,770 BBLS.
CHIPS HAULED 2,942  TONS 
OIL USED HFE/PPE 35,605 Gal / 7,070 Gal
ROADS CHIP SEALED (Working on S. Maddox) 0
TREE TRIMMING 6   DAYS
TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

289.8 MILES

CATTLE GUARD CREW  
GUARDS CLEANED 8
GUARDS REPAIRED  2
GUARDS RE-SET 1
GUARD REPLACED 2
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 1,151.02 TONS
BASE MATERIAL MOVED TO LOADING AREA 1,572.28 TONS
MATERIAL  LOADED FOR ROADWAYS 725.82 TONS
PIT RUN  
PUSHED UP 840 TONS
PIT RUN MOVED TO STOCK PILE  561.51 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 678.86 TONS
PIT RUN FROM COUNTRY CLUB 214 TONS
N.M.ONE CALLS    
ONE CALLS MADE 184
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

1
911 SIGNS MISSING REPLACED 12
SIGNS REPLACED MISSING 8
SIGNS REPLACED DAMAGED 18
SIGN AND POST INSTALLATION 6
COUNTY MOWING   
NO MOWING ACTIVITY  
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 64 PROJECTS
WELDING SHOP ACTIVITIES 7 PROJECTS
MECHANIC WORK 37 UNITS
SHOP SERVICE 45 UNITS
FIELD SERVICE 10 UNITS

 

Return to Road Home

Return to top of page

 

 

RECORD FOR MONTHLY REPORT JUNE 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 1
BASE HAULED

934 TONS

PIT RUN HAULED 0 TONS
ASPHALT ROADS WORKED ON 4
PATCH YARDS USED (using Dura Patcher)

7  YARDS

BBLS.WATER 5,280 BBLS.
CHIPS HAULED 5,703 TONS 
OIL USED HFE/PPE 11,370 Gal HFE / 1,500 Gal PPE (PRIME)
ROADS CHIP SEALED (Working on S. Maddox) GEORGIA, ILLINOIS, CHANCE
TREE TRIMMING 10   DAYS
TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

MILES

CATTLE GUARD CREW  
GUARDS CLEANED 6
GUARDS REPAIRED  2
GUARDS RE-SET 4
GUARD REPLACED 1
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 5,280 TONS
BASE MATERIAL MOVED TO LOADING AREA 5,000 TONS
MATERIAL  LOADED FOR ROADWAYS 9,486 TONS
PIT RUN  
PUSHED UP 2,400 TONS
PIT RUN MOVED TO STOCK PILE  906 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 486 TONS
PIT RUN FROM COUNTRY CLUB 0 TONS
N.M.ONE CALLS    
ONE CALLS MADE 206
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

3
911 SIGNS MISSING REPLACED 4
SIGNS REPLACED MISSING 6
SIGNS REPLACED DAMAGED 12
SIGN AND POST INSTALLATION 8
COUNTY MOWING   
NO MOWING ACTIVITY  
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 52 PROJECTS
WELDING SHOP ACTIVITIES 4 PROJECTS
MECHANIC WORK 35 UNITS
SHOP SERVICE 42 UNITS
FIELD SERVICE 8 UNITS

 

Return to Road Home

Return to top of page

 

 

RECORD FOR MONTHLY REPORT JULY 2008
   

ASPHALT CREW

 
CALICHE ROADS WORKED ON 1
BASE HAULED

4,803.5 TONS

PIT RUN HAULED 0 TONS
ASPHALT ROADS WORKED ON 0
PATCH YARDS USED (using Dura Patcher)

61.5  YARDS

BBLS.WATER 3,120 BBLS.
CHIPS HAULED 2,366 TONS 
OIL USED HFE/PPE 17,872 Gal HFE / 11,000 Gal PPE (PRIME)
ROADS CHIP SEALED (Working on S. Maddox) MARLEE
TREE TRIMMING 0 DAYS
TUMBLEWEED CLEAN UP

 0 DAYS

BLADE ROUTES  
MILES BLADED

 MILES

CATTLE GUARD CREW  
GUARDS CLEANED 12
GUARDS REPAIRED  3
GUARDS RE-SET 2
GUARD REPLACED 3
CRUSHER CREW  
MATERIAL CRUSHED/RECLAIMER 3,707 TONS
BASE MATERIAL MOVED TO LOADING AREA 5,034 TONS
MATERIAL  LOADED FOR ROADWAYS 4,353 TONS
PIT RUN  
PUSHED UP 900 TONS
PIT RUN MOVED TO STOCK PILE  773 TONS
BASE MATERIAL SHIPPED TO HOBBS YARD 0 TONS
PIT RUN FROM COUNTRY CLUB 0 TONS
N.M.ONE CALLS    
ONE CALLS MADE 175
TICKET VIOLATIONS FAXED TO PIPELINE DIVISION 0
SIGN CREW   

-    911 SIGNS INSTALLED ( NEW )

4
911 SIGNS MISSING REPLACED 20
SIGNS REPLACED MISSING 30
SIGNS REPLACED DAMAGED 1
SIGN AND POST INSTALLATION 7
COUNTY MOWING   
MOWING ACTIVITY 4 DAYS
WELDING SHOP ACTIVITIES  
TIRE SERVICE, REPAIRS ON EQUIPMENT 39 PROJECTS
WELDING SHOP ACTIVITIES 6 PROJECTS
MECHANIC WORK 45 UNITS
SHOP SERVICE 30 UNITS
FIELD SERVICE 6 UNITS

 

Return to Road Home

Return to top of page

 

 

RECORD FOR MONTHLY REPORT AUGUST 2008
 

CURRENT

MO./AVG

YTD

ASPHALT CREW

     
CALICHE ROADS WORKED ON 0 1 1
BASE HAULED TONS 690 2,747

5,493

PIT RUN HAULED TONS 0 0 0
BBLS. WATER HAULED 1,600 2,933 5,866
CALICHE ROADS WORKED W/RECLAIMER 0 0

0

ASPHALT ROADS WORKED W/RECLAIMER 0 0 0
PATCHING W/DURA PATCHER /YARDS 29 45 90
PATCHING W/COLD MIX 0 0 0
CHIPS HAULED TONS 7,602 4,984 9,968
PRIME OIL USED / GALLONS 200 5,600 11,200
HFE - 100 OIL USED 168,325 93,099

186,197

ROADS CHIP SEALED 4 3 5
TREE TRIMMING      
NUMBER OF DAYS WORKED 4 4 4
BLADE ROUTES      
NUMBER OF MILES BLADED 276 292

584

CATTLE GUARD CREW      
GUARDS CLEANED 6 9 18
GUARDS REPAIRED 3 3 6
GUARDS RE-SET 2 2 4
GUARD REPLACED 1 2 4
CRUSHER CREW      
MATERIAL CRUSHED FOR BASE / TONS 1,080 2,394 4,787
BASE MATERIAL TO LOADING AREA / TONS 5,034 5,034 5,034
BASE LOADED FOR ROADWAYS / TONS 909 2,631 5,262
BASE HAULED TO HOBBS YARD / TONS 0 0 0
PIT RUN      
PIT RUN RIPPED IN PIT / TONS 9.000 4950 9,900
PIT RUN PUSHED UP / TONS 9,000 4950 9,900
PIT RUN TO CRUSHER FEED PILE / TONS 6,195 3,484 6,968
PIT RUN FOR ROADWAY USE / TONS 0 0 0
N.M.ONE CALLS        
NUMBER OF ONE CALLS MADE 189 182 364
       
SIGN CREW       

-    911 NAME SIGNS INSTALLED NEW ROADS

2 3 6
911 NAME SIGNS MISSING REPLACED 6 13 26
MISSING ROAD SIGNS REPLACED 6 13 26
DAMAGED ROAD SIGNS REPLACED 7 4 8
SIGN AND POST INSTALLATION 5 5 10
NEW REFLECTIVE SIGNS INSTALLED 6 16 31
COUNTY MOWING       
DAYS MOWED 16 12 24
WELDING SHOP ACTIVITIES      
WELDING PROJECTS AT SHOP 0 3 6
WELDING PROJECTS IN THE FIELD      
SHOP      
TIRE REPAIRS 27 33 66
TIRE MAN REPAIRS MADE ON EQUIPMENT 2 2 4
UNITS SERVICED BY FUEL TRUCK 5 6 11
UNITS SERVICED IN SHOP/OIL CHANGE 15 23 45
MECHANIC WORK      
MECHANIC WORK 31 38 76
# 35 CHEVY 1 TON P/U  
DATE: 8-13-08 TIME:7:00  
PROBLEM: NOISE AND BURNT SMELL    
REMOVED GLOVE BOX,REMOVED EMC COMPUTER,REMOVED COMPUTER BRACKET,  
REMOVED BLOWER MOTOR SOUND COVER,REMOVED BLOWER MOTOR ASSEMBLEY,  
CALLED WATSON'S FOR PARTS AND PICKED UP, REPLACED BLOWER MOTOR  
PROBLEM CORRECTED 10:30 A.M.  
# 11 P/U 2002 DODGE RAM 250  
DATE: 8-13-08  TIME: 10:45  
PROBLEM: LONG CRANKING TIME, ACTING LIKE IT DOESN'T WANT TO START  
HAS A PO216 INJECTION CONTROL CIRCUT MALFUNCTION, NEEDS NEW INJECTION PUMP  
ORDERED NEW PUMP WILL BE IN 8-18-08, WILL TAKE 1-2 DAYS TO INSTALL AND RE-SET.  
11:30 A.M.  
G-11 BLADE  
DATE:8-13-08  TIME: 1:28 P.M.   
PROBLEM: BLADE DIED ON HIGHWAY WHILE EN ROUTE TO JOBSITE   
BLEED DIESEL SYSTEM, HAD AIR IN SYSTEM. 2:00 P.M.  
G-14 BLADE  
DATE:8-14-08   TIME: 8:45 A.M.  
PROBLEM: BLADE WOULD NOT START, AND HAD FLAT TIRE  
TIRE MAN REPAIRED TIRE, WE JUMP STARTED BLADE AND BROUGHT BACK TO YARD  
FOR CLEAN UP.  11:07 A.M.  
BROOM # 3  
DATE: 8-14-08  TIME 11:25 A.M.  
PROBLEM: A/C NOT WORKING  
TRACED PROBLEM, FOUND LOOSE FUSE BOX, TIGHTENED FUSE BOX   
AND FUSE CONNECTORS  NOTE: MAY NEED NEW FUSE BOX  
12:40 P.M.  
 
# 11 P/U  
DATE:8-18-08   TIME:7:00 A.M.  
START ON INJECTION PUMP REMOVAL, PUMP COMING FROM ODESSA TX.  
COMPLETED TAKING OFF PUMP  11:30 A.M.  
LOADER #7  
DATE: 8-19-08   TIME 9:00 A.M.  
UNIT NEEDS NEW ANTENNA AND BEACON LIGHT  
REMOVE PLASTIC COVERON TOP OF LOADERAND REPLACED BEACON LIGHT AND   
REWIRED SYSTEM,REPLACED RADIO ANTENNA 10:45 A.M.  
UNIT # 27  
DATE: 8-19-08   TIME: 11:00 A.M.   
REMOVED COVER ON DISTRIBUTOR TO REPLACE SQUARE OIL STRAINER ON BACK OF  
OIL BOX   2:30  P.M.  
UNIT # 42  
DATE: 8-19-08   TIME: 3:00 P.M.   
ALTENATOR AND ALL GUAGES QUIT WORKING, REMOVED ALTENATOR AND  
INSTALLED NEW ONE  4:30 P.M.  
UNIT # 11  
DATE: 8-20-08  TIME:7:30 A.M.  
START INSTALLATION OF NEW INJECTION PUMP  5:00 P.M.  
UNIT # 11  
DATE:8-21-08   TIME: 7:00 A.M.  
FINISH INSTALLING INJECTION PUMP, TIMED PUMP AND CHECKED FOR CODES  
WITH SCAN TOOLS NO CODES IN SYSTEM, TEST DRIVE TRUCK ALL OK  12:00 P.M.  
UNIT # 3  
DATE: 8:35 A.M.  TIME: 7:15 A.M.  
HAUL TRUCK WOULD NOT START  
PROBLEM SOLVED CHARGED BATTERIES TRUCK RAN FINE ALL DAY 11:15 A.M.  
G-10 BLADE  
DATE: 8-25-08  TIME: 12:45 P.M.  
PROBLEM BROKEN BOLTS, REMOVED BROKEN BOLTS ON MOLD BOARD CYLINDER  
REPLACED WITH NEW ONES, ALSO TRACED A SHORT THAT WAS CAUSING  
SAFETY LIGHTS TO MALFUNCTION, INSTALLED NEW FUSE  4:30 P.M.  
LOADER # 4  
DATE: 8-26-08   TIME: 7:15 A.M.  
DROVE TO CRUSHER SITE, REMOVED TWO WAY RADIO CABLE AND REPLACED IT   
WITH A NEW ONE, ALSO INSTALLED TWO WAY RADIO AND NEW ANTENNA  11:30 A.M.  
CONVIENANCE CENTER OLD BACKHOE  
DATE: 8-26-08   TIME: 12:15 P.M.  
TOPPED OFF TRANSMISSION FLUID,ADDED COOLANT, MOVED TO ROAD DEPT.  
FOR SERVICE CHECK-UP 2:00 P.M.  
 
MOWER #2  
DATE: 8-26-08  TIME 2:15 P.M.  
PROBLEM: BRACKETS ON BATTERY BOX BROKEN  
REPAIRED BRACKETT AND REINSTALLED BATTERIES AND COVER 3:57 P.M.   
LOADER #5  
DATE: 8-26-08   TIME: 4:00 P.M.  
HELPED ROBERT REPLACE TWO WAY RADIO CABLE AND ANTENNA 4:25 P.M.  
ALSO  
UNIT # 33  
PROBLEM:BATTERIES DOWN TWO WAY RADIO LEFT ON  
JUMPED TRUCK OFF LET BATTERIES CHARGE  4:35 P.M.  
UNIT # 27 DISTRIBUTOR  
DATE:8-27-08   TIME: 7:15 A.M.   
REMOVED REAR CYLINDER THAT WAS LOOSING AIR PRESSURE AND REPLACED WITH  
A NEW ONE, ALSO REPLACED ELECTRICAL PART IN SAME AREA. 11:50 A.M.  
UNIT # 49  
DATE: 8-13-08   TIME: 11:30 A.M.  
REPLACED TARP, ROAD CHECKED OIL LEAK, WASH AND CLEANED 2:30 P.M.  
UNIT # G-12 BLADE  
DATE: 8-13-08   TIME 9:00 A.M.  
INSTALL NEW SAFETY LIGHT ON BACK OF UNIT 11:00 A.M.  
BANDIT WOOD CHIPPER  
DATE: 8-21-08  TIME: 1:00 P.M.  
INSTALL NEW BELTS  4:30 P.M.  
UNIT MOWER #2  
DATE: 8-18-08  TIME: 7:00 A.M.  
CHECK M-2 ENGINE FOUND BAD FUEL FILTER, REPLACED FILTERS 10:00 A.M.  
UNIT # 17 WATER TRUCK  
DATE: 8-18-08   1 1/2 HOURS  
PULLED WATER TANK OFF TRUCK  
UNIT # 31  
DATE: 8-18-08   2 1/2 HOURS  
PULLED TRANSMISSION AND REPLACED MAIN CLUTCH  
UNIT # 40  
DATE: 8-19-08  7:00 A.M.  
REPAIRED AIR LEAK AND REPLACED VALVE 8:30 P.M.  
UNIT # 4  
DATE: 8-19-08    
INSTALL NEW FRONT BUMPER  2 HOURS  
 
UNIT # 17 WATER TRUCK  
DATE: 8-19-08  
REPLACED TANK PADS ON TRUCK  4 HOURS  
UNIT # ROLLER 4  
DATE: 8-21-08     
CHECK CHARGING SYSTEM AND REPLACED ALTENATOR  
UNIT # 31  
DATE: 8-23-08  
INSTALL NEW CLUTCH IN TRUCK  3 1/2 HOURS  
INSTALL DRIVE LINE ADJUST CLUTCH AND ROAD TEST 2 1/2 HOURS  
UNIT # 44  
DATE: 8-23-08  
REPLACE HYD. HOSES, REPLACE 1/8 INCH SAFETY CABLE 2 HOURS  

 

 